SOURCE-LINKED U.S. REGISTRY

Metrobloks Southfield Data Center

Metrobloks · Southfield, MI · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
42.474, -83.293
Serving utility, source-reported
DTE Energy
Operational capacity, source-reported
Not published
Planned capacity, source-reported
100 MW
Source record updated
2026-10-24

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

217,030-230,000 sq ft, two-story building on ~12.19 acres of vacant land along Inkster Road north of 11 Mile Road, Southfield's northwest corner. Los Angeles-based developer Metrobloks (as of August 2026, already tracked elsewhere in MO/IN/FL) has not completed a data center build anywhere yet per reporting. City of Southfield's own statement explicitly says the facility is not intended as 'an artificial intelligence repository' -- an AI classification is omitted here rather than defaulting to likely AI-specific. City Council approved the site plan 5-2 on Dec 16, 2025; the city notes 'Approval of the proposal does not remove City oversight' -- still subject to further permitting. A named IT-engineer public commenter said the real target may be closer to 150 MW by groundbreaking; unconfirmed beyond that public comment. Closed-loop cooling planned, city says 'minimal long-term water use.' Coordinates are an approximate Inkster/11 Mile intersection estimate, not parcel-geocoded.

DTE must deliver power before construction can begin, possibly 2027 or 2028

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory