Microsoft Granger Data Center

Microsoft · Granger, IN · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.73, -86.13
Serving utility, source-reported
Indiana Michigan Power (I&M / AEP)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
1000 MW
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Microsoft acquires 939-acre St. Joe Farm near Currant and Cleveland Roads, Granger IN for $77.5M; site adjacent to Indiana Toll Road; county rezones land

    Underlying source
  2. Permitted

    St. Joseph County Redevelopment Commission and City of Mishawaka approve MOU for pre-development work; $12.6M cap for early design and infrastructure evaluation; construction authorization pending resolution of utility and site plan questions

    Underlying source
  3. Under construction

    Construction underway as of late May 2026: WVPE reported on May 30, 2026 that Microsoft was trucking water into the site to suppress dust and that the county highway department was inspecting construction truck traffic. Follows the St. Joseph County MOU approval (March 17, 2026); WSBT reported in March 2026 that construction could begin in late April or early May, and as of October 2026 no source found gives the actual start date.

    Underlying source

Source notes

Former St. Joe Farm, near Bittersweet Road and Currant Road, Granger IN (St. Joseph County). 939 acres; 5-6 buildings planned; ~1 GW power load estimated by county officials. Microsoft not seeking local tax incentives. WSBT reported on February 18, 2026 that a formal site plan had not been submitted and that many project details still had to be worked out before construction could begin; WNDU March 2026 MOU covers pre-development evaluation only. WVPE reported on May 30, 2026 that construction was underway, with water trucked in for dust suppression. The record is marked reported. Coordinates are approximate Granger unincorporated community area.

Grid-served; Microsoft is named among large-load customers in I&M's 2024 settlement. No on-site generation reported.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.