Microsoft Heath Data Center

Microsoft · Heath, OH · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
975 Thornwood Dr
Coordinates
40.015, -82.46
Serving utility, source-reported
AEP OhioView utility impact evidence
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Announced as part of $1B Licking County investment; Microsoft purchases 227 acres at 975 Thornwood Dr SW, Heath for over $32M

    Underlying source
  2. Proposed

    Microsoft pauses all Licking County sites

  3. Under construction

    Groundbreaking February 24, 2026; AMES Construction as general contractor; mass grading began February, targeted complete November 2026

    Underlying source

Source notes

Site at 975 Thornwood Dr SW, Heath OH 43056; 227 acres. Part of Microsoft's $1B Licking County three-campus investment alongside Hebron and New Albany. Coordinates are approximate Heath city centroid; exact Thornwood Dr parcel not pinned. The $1B is Microsoft's three-campus Licking County commitment; no Heath-specific capital-investment figure is published (do not derive by subtraction).

Powered from the AEP Ohio grid as part of Microsoft's Central Ohio (Licking County) expansion.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.