Mid-County Industrial Park Data Center Campus
Minnieville Capital Acquisitions · , VA · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.6320976, -77.4218513
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-14
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Permitted
Board of County Supervisors approved 5-3: about 40 acres rezoned from agricultural to industrial plus ~20 acres in Colchester Industrial Park.
Underlying source
Source notes
Three data center buildings and an electric substation, about 250 feet northwest of the Dumfries Road (Route 234) and Minnieville Road intersection, with buildings nearest Route 234 capped at 75 feet. Press has linked a Minnieville-tied buyer to an Amazon P.O. box, but end-user identity is not confirmed. The coordinates are an approximate point on Dumfries Road at Independent Hill, not the parcel.
Sources and provenance
- Prince William supervisors approve contentious Mid-County Industrial Park data center project · source retrieved 2026-10-14
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.