Nebius Vineland Data Center
Nebius Group · Vineland, NJ · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- South Lincoln Avenue
- Coordinates
- 39.4862, -74.992
- Serving utility, source-reported
- Vineland Municipal Utilities Authority (supplemental, ~15%)
- Operational capacity, source-reported
- 100 MW
- Planned capacity, source-reported
- 300 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
First phase completed in approximately 20 weeks (summer 2025); Nebius committed to 100 MW installed capacity by year-end 2025; Microsoft GPU capacity deliveries begin late 2025. Full campus buildout targeting November 2026.
Underlying source - Proposed
Nebius and DataOne announce phased AI data center in Vineland, NJ; 20-week first-phase build target, total ceiling 'up to 300 MW'
Underlying source
Source notes
Phase-1 (~100 MW) completed summer 2025 in approximately 20 weeks from March 2025 announcement; full campus buildout targeting November 2026. Total design capacity cited as 'up to 300 MW' in Nebius press releases; DataOne CEO and local/community coverage consistently cite 350 MW; long-term campus potential described as approaching 1 GW. Coordinates are approximate (site: South Lincoln and Sheridan Avenues, East Vineland; Baxtel lists 805 Sheridan Ave). DataOne is the developer/builder — BSO's data center unit (launched 2024) backed by Ardian; CEO Charles-Antoine Beyney; this is DataOne's first US site (previously Grenoble and Lyon, France). Nebius is the ~10-year tenant; Microsoft GPU infrastructure agreement commencing late 2025 under multi-year AI infrastructure deal. Facility is 100% privately funded; DataOne declined a $6.2M city equipment loan amid community backlash. Distinct from Nebius's Independence, MO (Kansas City) site. NJDEP air permit pending as of early 2026; construction proceeded ahead of final permit issuance. DataOne stated 200+ permanent full-time jobs. As of October 2026, Nebius's project page states roughly 200 permanent on-site jobs and roughly 1,000 jobs during construction.
32 high-efficiency natural gas engines generate approximately 85% of facility power; 6 diesel generators for backup. Proposed 1.5-million-gallon LNG storage tank as pipeline contingency (pending approval). NJDEP air permit under review as of early 2026; Sierra Club and Pinelands Alliance objecting to emissions profile. Facility located in Wellhead Protected Area near Kirkwood-Cohansey aquifer.
Sources and provenance
- Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey · source retrieved 2026-07-07
- We're introducing the 300 MW New Jersey region and expanding to Iceland · source retrieved 2026-07-07
- DataOne to build Nebius data center in New Jersey · source retrieved 2026-07-07
- Vineland residents are protesting AI data center as concerns mount over emissions · source retrieved 2026-07-07
- A Town Hall Too Late – Vineland Data Center · source retrieved 2026-07-07
- South Jersey's largest data center is being built in Vineland. Some residents say they've had no say in the process. · source retrieved 2026-07-07
- 'Vineland data center makes case for on-site power generation during 6-hour hearing' — WHYY, 6 August 2026 · source retrieved 2026-09-14
- 'Vineland planning board approves 2nd phase of 300-megawatt data center plan' — WHYY, 18 August 2026 · source retrieved 2026-09-14
- What exactly is DataOne building in Vineland? · source retrieved 2026-09-21
- Nebius x Vineland, New Jersey · source retrieved 2026-09-21
- City of Vineland, N.J. issues stop-work order to parts of data center · source retrieved 2026-09-21
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.