Nebius Vineland Data Center

Nebius Group · Vineland, NJ · United States

Facility record

Lifecycle
OperationalSource-reported lifecycle
Location precision
approximate
Address as listed
South Lincoln Avenue
Coordinates
39.4862, -74.992
Serving utility, source-reported
Vineland Municipal Utilities Authority (supplemental, ~15%)
Operational capacity, source-reported
100 MW
Planned capacity, source-reported
300 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Operational

    First phase completed in approximately 20 weeks (summer 2025); Nebius committed to 100 MW installed capacity by year-end 2025; Microsoft GPU capacity deliveries begin late 2025. Full campus buildout targeting November 2026.

    Underlying source
  2. Proposed

    Nebius and DataOne announce phased AI data center in Vineland, NJ; 20-week first-phase build target, total ceiling 'up to 300 MW'

    Underlying source

Source notes

Phase-1 (~100 MW) completed summer 2025 in approximately 20 weeks from March 2025 announcement; full campus buildout targeting November 2026. Total design capacity cited as 'up to 300 MW' in Nebius press releases; DataOne CEO and local/community coverage consistently cite 350 MW; long-term campus potential described as approaching 1 GW. Coordinates are approximate (site: South Lincoln and Sheridan Avenues, East Vineland; Baxtel lists 805 Sheridan Ave). DataOne is the developer/builder — BSO's data center unit (launched 2024) backed by Ardian; CEO Charles-Antoine Beyney; this is DataOne's first US site (previously Grenoble and Lyon, France). Nebius is the ~10-year tenant; Microsoft GPU infrastructure agreement commencing late 2025 under multi-year AI infrastructure deal. Facility is 100% privately funded; DataOne declined a $6.2M city equipment loan amid community backlash. Distinct from Nebius's Independence, MO (Kansas City) site. NJDEP air permit pending as of early 2026; construction proceeded ahead of final permit issuance. DataOne stated 200+ permanent full-time jobs. As of October 2026, Nebius's project page states roughly 200 permanent on-site jobs and roughly 1,000 jobs during construction.

32 high-efficiency natural gas engines generate approximately 85% of facility power; 6 diesel generators for backup. Proposed 1.5-million-gallon LNG storage tank as pipeline contingency (pending approval). NJDEP air permit under review as of early 2026; Sierra Club and Pinelands Alliance objecting to emissions profile. Facility located in Wellhead Protected Area near Kirkwood-Cohansey aquifer.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.