Former Emerson Campus Data Center (Next Revolution Technologies)
Next Revolution Technologies LLC · Ferguson, MO · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.744707, -90.3038975
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 300 MW
- Source record updated
- 2026-11-02
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Ferguson City Council approved 4-3 a redevelopment and tax-incentive plan for the former Emerson Electric campus. It includes a potential future expansion to a 300 MW data center, after a similar plan failed 3-3 in May 2026.
Underlying source
Source notes
217-acre former Emerson Electric campus in Ferguson, bought in 2026 by Next Revolution Technologies LLC (run by Onder Law's James Onder). The campus already has a smaller data center; the approved plan includes renovating it and a potential future 300 MW data center (the planned capacity reflects that potential expansion). Up to $22B in industrial revenue bonds authorized. Community payments: $700K to the city, $250K environmental mitigation fund, $7.5M over 10 years to the Ferguson Neighborhood Improvement Program. Coordinates are the Ferguson municipal centroid (approximate); no street address was given in the cited sources. The record is listed as proposed: the council approval is a tax-incentive/redevelopment package, not a building permit.
Sources and provenance
- Ferguson City Council says yes to tax breaks for data center development · source retrieved 2026-11-02
- Ferguson tax break plan for data center, Emerson redevelopment · source retrieved 2026-10-13
- OpenStreetMap Nominatim geocode: Ferguson, Missouri · source retrieved 2026-10-13
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.