Niagara Digital Campus

Urbacon Data Centre Solutions · Niagara Falls, NY · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
43.0885, -79.0603
Serving utility, source-reported
New York Power Authority (NYPA)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
135 MW
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Niagara Falls Redevelopment (NFR) and Urbacon Data Centre Solutions announce $1.5B campus proposal at Rainbow and John B. Daly Boulevards

    Underlying source
  2. Proposed

    Planning Board rejects modified application; parties reported near resolution including possible two-project accommodation

    Underlying source
  3. Proposed

    New application incorporating additional Falls Street parcels under review; NFR states construction could begin within six months of approvals

    Underlying source

Source notes

Site is near the historic Adams Power Plant and the NYPA Robert Moses Niagara Power Plant (2,675 MW combined capacity). Phase I planned as ~282,000 sq ft over 24 months from groundbreaking. Economic impact estimated at $2B over 20 years per MRB Group analysis commissioned by NFR. Developed by Niagara Falls Redevelopment (NFR, controlled by Milstein family) in partnership with Urbacon. No status change. The 4 June 2026 City Council vote settled an eminent-domain lawsuit and transferred 10 acres to the city; the mayor states explicitly it was not a data-center approval and that there is no timeline for work to begin. Remains proposed.

Site at 907 Falls St (Rainbow and John B. Daly Blvd); 600,000 sq ft across two phases; new electrical substation planned for the campus.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.