SOURCE-LINKED U.S. REGISTRY

Nine Mile Data Center (Uinta Basin Data Center Project)

Nine Mile Data, LLC · Myton, UT · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
40.193, -110.0568
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-09-21

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    Duchesne County Planning Commission approved conditional-use permits for the data center and related Wells Draw Energy/reWater facilities.

    Underlying source

Source notes

Approximately 6 miles southwest of Myton near Wells Draw and South Myton Bench; ~475 acres for data-center use within a ~879-acre leased area; targeting operational by 2029. Subsidies checked at the municipal tier (2026-09-04): no site-level subsidy. The county's conditional-use findings report carries no tax-abatement, CRA/RDA or payment-in-lieu-of-taxes term, and no Duchesne County or Myton CRA project area was found to exist at all. Utah's EDTIF programme excludes data centres and the UCA 59-12-104 exemption is self-executing.

On-site power via Wells Draw Energy's 400MW natural gas plant plus a 333MW solar photovoltaic plant and 800-1,600MWh of battery storage.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory