Deep Park Data Center (North Port 300)
North Port Holdings 300 LLC (end operator undisclosed) · North Port, FL · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 27.0677773, -82.0743791
- Serving utility, source-reported
- Florida Power & Light
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-20
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Site and development plan application received by the City of North Port; city awaiting applicant response to sufficiency-review deficiencies.
Underlying source
Source notes
Seven data center buildings totaling ~896,000 sq ft (incl. ~123,200 sq ft office) on ~112 acres within the 282-acre 'Deep Park' master concept (Activity Center 6) north of I-75 and south of Yorkshire Street. Applicant LLC is registered to Valley Stream, NY; end tenant is under NDA. Application filed 2026-07-20; ~22.5 acres of stormwater ponds and 4.14 acres of wetland impacts per filings.
FPL is the electric provider per the filings. FPL has not confirmed that the project has begun large-load review. A future substation is planned as a separate submission, and no definitive electrical load is stated.
Sources and provenance
- North Port releases new information on proposed data center as commission considers moratorium · source retrieved 2026-09-21
- New North Port data center filings detail water use, wetland impacts and more · source retrieved 2026-10-20
- Proposed North Port data center location found? · source retrieved 2026-09-21
- City of North Port — Data Center Info (application timeline) · source retrieved 2026-09-21
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.