NorthMark Strategies Spartanburg High-Performance Computing Center
Valara Holdings (NorthMark Strategies) · Spartanburg, SC · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 4000 South Pine Street
- Coordinates
- 34.923066, -81.851905
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 450 MW
- Source record updated
- 2026-10-27
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Facility in development at the former Kohler manufacturing plant in Spartanburg County; slated to go online later in 2026.
Underlying source
Source notes
Adaptive reuse of the former Kohler manufacturing facility in Spartanburg County, developed by NorthMark Strategies through its subsidiary Valara Holdings. This is a DIFFERENT Spartanburg County site from the tracked Greenidge record at 300 Jones Road. Coordinates are an approximate geocode of the South Pine Street address reported in local coverage; no parcel-level source was retrieved. Subsidies checked 2026-09-10: Spartanburg County Council approved a tax incentive package for the project, but the article does not give a FILOT dollar figure or program name -- only projected resulting property-tax revenue ($10.5M in 2026 rising to $15M/yr 2029-2045). Not filing a structured subsidies entry since no incentive amount is stated; flagging for a follow-up pass that can find the actual FILOT ordinance.
The project is being built with on-site power generation rather than drawing the full load from the local grid. NorthMark applied to the S.C. Department of Environmental Services on 2026-03-04 for 'additional equipment to support increased power generation capacity' at the site; the application was under technical review as of April 2026.
Sources and provenance
- Spartanburg data center requests additional equipment for larger power capacity · source retrieved 2026-08-26
- OpenStreetMap Nominatim geocode for 4000 South Pine Street, Spartanburg, SC · source retrieved 2026-08-26
- Energy and water use, projected jobs and revenue: Spartanburg's NorthMark data center by the numbers · source retrieved 2026-09-10
- Air - Construction Permit (Modification), Submission HQJ-32R0-VR9VC — Valara Holdings High Performance Compute Center · source retrieved 2026-09-13
- What the Drafts Let Us See (Valara development agreement drafts) · source retrieved 2026-10-27
- Fact Sheet: Valara Holdings High Performance Compute Center Air Quality Construction Permits · source retrieved 2026-10-27
- Residents sue over data center permits, seek utility regulator scrutiny of natural gas plant · source retrieved 2026-10-27
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.