Novva Mesa Data Center Campus
Novva Data Centers · Mesa, AZ · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 33.3717, -111.6747
- Serving utility, source-reported
- Salt River Project (SRP)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 300 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Novva won 165-acre Mesa state land auction for $62.7M; campus previously filed under name Project Borealis
Underlying source - Under construction
Construction underway; Phase 1 (96MW critical IT load) targeting late 2026 opening
Underlying source
Source notes
Located near Ellsworth and Warner roads, southeast Mesa. Five data halls, 1.3M sq ft data hall space, 200,000 sq ft office, two-phase buildout over ~10 years. Sixth Novva campus nationally, first in Arizona. Architectural design honors Hohokam heritage. Coordinates approximate. Public-reception check (2026-09-10): Checked Novva's own announcement page (2026-09-10); it markets design amenities ('dedicated acreage offering public pathways for the community') but documents no actual public hearing, resident feedback, or official statement of support/opposition. No community-reception record found in this source.
100% renewable energy goal; backup generators designed for second-generation biofuel and HVO
Sources and provenance
- Novva Data Centers Announces New Campus in Mesa · source retrieved 2026-07-06
- Novva confirmed as behind Project Borealis data center campus in Phoenix · source retrieved 2026-07-06
- City of Mesa case ZON24-00291 ('Project Borealis') Project Narrative — 'Each of the data hall buildings will utilize a closed-loop water cooling system... Crucially, no evaporative methods are used for reducing air temperature' · source retrieved 2026-08-31
- City of Mesa Planning Division staff report, ZON24-00291 — 'Site Size: 159± acres', parcel 304-31-141 · source retrieved 2026-08-31
- Novva Data Centers Announces New Campus in Mesa · source retrieved 2026-09-23
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.