Novva Tahoe Reno Data Center
Novva Data Centers · McCarran, NV · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 39.53, -119.44
- Serving utility, source-reported
- NV Energy
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 60 MW
- Source record updated
- 2026-09-24
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Operational
Novva announced Tahoe Reno officially open for business — its fourth completed data center; additional capacity phasing into 2026.
Underlying source
Source notes
300,000 sq ft, 60 MW data center on a 20-acre campus at 1 Astro Way in the Tahoe-Reno Industrial Center (McCarran / Storey County). Six 10 MW data halls served by an on-campus 100 MW NV Energy substation; water-free direct-to-chip cooling. Coordinates are an approximate TRIC-area geocode (exact parcel point not published).
Powered via a centralized on-campus 100 MW substation (N+1 redundancy) fed by NV Energy; facility seeks local renewable energy credits.
Sources and provenance
- Novva Data Centers Announces the Launch of Tahoe Reno Data Center (PR Newswire) · source retrieved 2026-07-15
- American data center operator Novva launches facility in Nevada (DCD) · source retrieved 2026-07-15
- Novva Tahoe Reno Data Center — 1 Astro Way (60 MW), Storey County · source retrieved 2026-07-15
- Novva Data Centers Tahoe Reno — launch of Tahoe Reno data center · source retrieved 2026-08-14
- Data Centers in Nevada — project list (Novva Tahoe Reno, 60 MW, Storey County) · source retrieved 2026-09-24
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.