NTT Global Data Centers Mesa — Pacific Proving Technology Park
NTT Global Data Centers · Mesa, AZ · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 33.3025, -111.62
- Serving utility, source-reported
- Salt River Project (SRP)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 360 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Project first proposed as Pacific Proving Technology Park; NTT filed pre-submittal with City of Mesa
- Proposed
Mesa Planning Commission voted unanimously to recommend rezoning; council vote was pending summer 2026
Underlying source - Proposed
Mesa's Planning and Zoning Board voted 4-0 to recommend that City Council approve NTT's rezoning, council use permit and major site plan modification for the 170-acre site at Pecos and Crismon roads. A recommendation only — the Council decision had not been taken.
Underlying source
Source notes
The investment figure is $300M land purchase only; total buildout investment is substantially higher. NE corner of Pecos and Crismon roads, far SE Mesa. Seven two-story buildings totaling 1.7M sq ft + warehouse + office. NTT's second Phoenix-area campus (existing 102-acre, 240MW campus is ~4 miles north on Elliot Road). Phase 1 targeted November 2028. Coordinates approximate for Pecos/Crismon intersection. Status as of 2026-08-08: the Planning & Zoning Board recommended approval 4-0 in mid-May 2026; the article (updated 2026-06-08) said the proposal "will likely be heard in late July or mid-August by council". As of August 2026, no source consulted records a Council vote, so the record stays listed as proposed — the 2026-07-20 date carried in earlier notes was an expected hearing date, not a decision.
On-site SRP substation and private power substation proposed
Sources and provenance
- NTT acquires 173-acre planned data center park in Mesa for $300m · source retrieved 2026-07-06
- Mesa residents are fighting a Tokyo tech giant's data center · source retrieved 2026-07-06
- Big data center in SE Mesa passes first review — Planning & Zoning Board recommends approval 4-0 for the 170-acre site at Pecos and Crismon · source retrieved 2026-08-08
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.