SOURCE-LINKED U.S. REGISTRY

Beacon Falls Data Center Campus (1 Lopus Road)

O&G Industries · Beacon Falls, CT · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
1 Lopus Road
Coordinates
41.442318, -73.064334
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
100 MW
Source record updated
2026-09-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

O&G Industries (master developer) is marketing a 44+/49-acre former gravel-pit site off Lopus Road beside Route 8 for a 294,000 sq ft data center campus: 100 MW ultimate capacity (listing specs say 112.5 MW), sold as AI/cloud capacity and powered by utility service plus Class I fuel cells (33 fuel cells, per the Courant) with carbon capture. As of 2026-09-21 no formal application had been filed with the town. Residents approved a 32 MW data center on the same property in 2022, but it never materialized. No AI classification is recorded: the AI framing comes from a marketing listing, not a committed tenant.

Listing: utility-delivered power combined with Class I fuel cells and carbon capture; the Courant reports 33 fuel cells planned

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.