Bedington Campus
Penzance Management · , WV · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 39.554, -77.882
- Serving utility, source-reported
- Potomac Edison (FirstEnergy)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 600 MW
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Announced February 26, 2026 by Governor Morrisey; designated West Virginia's first High Impact Intelligence Center (enabling bypass of certain local zoning constraints); site preparation underway as of March 2026. No state funding involved.
Underlying source
Source notes
Falling Waters District, Berkeley County WV eastern panhandle — adjacent to Maryland border. 1.9 million sq ft at full buildout. Penzance (DC/NoVA developer) is also developing a Fairfax County VA campus reportedly pre-leased to Amazon. Coordinates approximate for Falling Waters area. As of 2026-09-10, status was unchanged (proposed). The most recent coverage found (wvgazettemail article, published 2026-02-28, updated 2026-09-04) reports no groundbreaking, permit, or construction start yet; a tenant announcement was still described as pending later in 2026. The street address remains unresolved: governor.wv.gov, WV Division of Economic Development, SEDC, and county/trade press coverage all describe only '548 acres in the Falling Waters District of Berkeley County' with no house number or parcel ID; Berkeley County GIS/assessor records could not be reached as of September 2026, so no street address is recorded rather than one approximated. As of 2026-09-10 the Governor's office states explicitly that no state funding was used for Bedington Campus. HB 2014's revenue-sharing formula (50% Personal Income Tax Reduction Fund / 30% host county / 10% all counties per capita / 5% Electric Grid Stabilization and Security Fund / 5% Economic Enhancement Grant Program) is a distribution of the taxes the facility itself will generate, not an incentive granted to the facility, so it is not recorded as a subsidy. As of September 2026, no county-level PILOT or abatement agreement was found in the sources checked (governor.wv.gov, WV DED, SEDC).
Governor described project as 'likely' grid-connected via existing electric utilities
Sources and provenance
- Governor Morrisey Announces $4 Billion Private Investment in WV's First High Impact Intelligence Center · source retrieved 2026-10-28
- D.C.-based real estate firm investing $4B for new data center development in Berkeley County, WV · source retrieved 2026-07-06
- Penzance targets 600MW data center campus in West Virginia · source retrieved 2026-07-06
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- WV MetroNews — Public speaks out on data center planned for Falling Waters area · source retrieved 2026-07-26
- $4 Billion Data Center Campus Planned for Berkeley County — "up to 600 megawatts of critical IT capacity" · source retrieved 2026-09-15
- Data center project planned in Bedington area of Berkeley County · source retrieved 2026-10-28
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.