Chantilly Premier
Penzance · Chantilly, VA · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- 4151 Auto Park Circle
- Coordinates
- 38.8943, -77.4311
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-09-09
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
Penzance broke ground on the three-story, roughly 236,000 sq ft facility after securing more than $100 million in construction financing from QuadReal Property Group; delivery targeted for the first half of 2027.
Underlying source
Source notes
Roughly 12-acre site adjacent to Chantilly Auto Park south of Route 50. The Fairfax County Board of Supervisors approved the rezoning 8-1 in January 2024 over neighbour objections about height, traffic and environmental impacts; the approval permitted either a 150,000 sq ft warehouse or a data center up to 402,000 sq ft, and the building under construction is 236,000 sq ft. Reported as fully preleased, tenant undisclosed.
Sources and provenance
- Developer breaks ground on $100M data center building in Chantilly · source retrieved 2026-09-09
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.