SOURCE-LINKED U.S. REGISTRY

PowerHouse Data Centers – Louisville (Camp Ground Road)

PowerHouse Data Centers · Louisville, KY · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
38.1953, -85.8485
Serving utility, source-reported
LG&E
Operational capacity, source-reported
Not published
Planned capacity, source-reported
402 MW
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    Construction expected to begin 2025; Planning Commission approves revised site plans 6-1 over community objection in March 2026

    Underlying source
  2. Proposed

    PowerHouse Data Centers and Poe Companies announce Louisville campus at 6001 Camp Ground Road; Kentucky's first hyperscale data center

    Underlying source
  3. Permitted

    Development Review Committee approves 4-0; property already zoned industrial, no Metro Council vote required

    Underlying source

Source notes

Address: 6001 Camp Ground Road, Louisville, KY; near Shively and the Rubbertown industrial district, less than 1 mile from the Ohio River. 153 acres confirmed by DCD. 1.6M sq ft total campus across seven buildings. Operator discussing tenants including major hyperscalers (Google, Amazon, Microsoft named in reports). End tenant not publicly disclosed at time of research. Fix: removed unconfirmed '50-year' duration from tax exemption description — program exists per Kentucky 2024 legislation but specific term length was not confirmed by any fetched source.

New LG&E switch station to be completed September 2026; initial 130 MW available October 2026; expandable from 335 MW to 402 MW

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.