PowerHouse Grand Prairie Campus
PowerHouse Data Centers · Grand Prairie, TX · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 32.62, -97.02
- Serving utility, source-reported
- Oncor
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 1800 MW
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Under construction
PowerHouse and Provident developing a 1.8 GW campus in the DFW area (Grand Prairie): 24 buildings across three phases, 1.8 GW switchyard
Underlying source
Source notes
1.8 GW DFW-area campus (Grand Prairie): 24 buildings across three phases with an on-site 1.8 GW switchyard. Grand Prairie spans Dallas/Tarrant/Ellis counties; the campus is in the Ellis County (southern) portion. Coordinates reflect the southern Grand Prairie / Ellis County zone. Provident cited 'at least $5B in direct construction impact' over the multi-year build-out (Bisnow) and ~$300M for one 360,000-sq-ft building (Dallas Innovates) - neither a confirmed campus capex pledge -> no investment figure is recorded. Ellis County adopted Chapter 312 abatement guidelines (~Oct 2025, $50M threshold); no executed abatement agreement for this campus was found.
On-site 1.8 GW switchyard; ERCOT approved the first 500 MW tranche. Provident CEO Leon Backes said the company spent 'the past two years working closely with ERCOT and Oncor.' Oncor is Ellis County's incumbent transmission/distribution utility.
Sources and provenance
- PowerHouse and Provident to develop 1.8GW campus in DFW, Texas · source retrieved 2026-07-07
- Provident, PowerHouse partner on 768-acre Texas data center campus · source retrieved 2026-07-08
- DOE-funded UTA project tackles cooling costs amid AI data center demand · source retrieved 2026-07-08
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.