SOURCE-LINKED U.S. REGISTRY

Project Arrowhead (Premier Data Center Development Irwin County Campus)

Premier Data Center Development, LLC · Mystic, GA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
31.6224192, -83.3351929
Serving utility, source-reported
Georgia Power
Operational capacity, source-reported
Not published
Planned capacity, source-reported
1250 MW
Source record updated
2026-10-14

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Development of Regional Impact application filed with the Georgia Department of Community Affairs.

    Underlying source

Source notes

Five-building campus totalling 4.22 million sq ft on approximately 1,000 acres outside Mystic. First phase targeted 2030, full build-out 2034. The $6bn figure is stated as an upper bound ("up to $6 billion"), not a committed investment. Part of the land was previously earmarked for the Irwin Forward Tech Park proposal, withdrawn in March 2026. A DRI filing is a review trigger, not an approval — no rezoning or interconnection award is confirmed. Coordinates are the Mystic community centroid (OSM Nominatim), not a parcel.

Georgia Power is conducting an energy study for the project; no interconnection agreement is reported.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory