Project Delta Data Center – Stokes County

Undisclosed (rezoning applicant: Engineered Land Solutions) · Walnut Cove, NC · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
36.282, -80.1494
Serving utility, source-reported
Duke Energy (Belews Creek proximity; no confirmed interconnection)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Engineered Land Solutions submitted rezoning application for 1,800 acres from agricultural/farm use to heavy industrial/commercial near Dan River and Belews Creek Coal Plant

  2. Permitted

    Stokes County Board of Commissioners approved rezoning 3-2 despite opposition from county Planning Board and residents

    Underlying source
  3. Permitted

    Lawsuit filed in Stokes County Superior Court by SCSJ and SELC seeking to invalidate rezoning

    Underlying source
  4. Proposed

    Stokes County Board of Commissioners voted to void January 12 rezoning and text amendment, citing statutory notice failures; project must restart via fully compliant new application

    Underlying source
  5. Permitted

    On Sept 14, 2026 the Stokes County commissioners voted 3-2 to rezone about 1,800 acres for Project Delta. This followed the voiding of the January approval, which forced Engineered Land Solutions to reapply.

    Underlying source

Source notes

Site on US Highway 311 and Tuttle Road near Belews Creek Coal Plant on Dan River. End operator/tenant not publicly identified; rezoning approved for unidentified operator per lawsuit. Rezoning voided April 14, 2026 after court challenge over statutory notice failures. Developer ELS plans to resubmit. Capacity and investment not disclosed. Coordinates are Walnut Cove city centroid.

Developer plans temporary on-site natural-gas generators until a Duke Energy grid connection becomes feasible; no confirmed interconnection agreement found. Environmental groups flagged methane/CO2 from continuous generator use.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.