SOURCE-LINKED U.S. REGISTRY

Project Ruby (Upatoi Data Center Campus)

Undisclosed end user (site pursued by Choose Columbus / Development Authority of Columbus) · Columbus, GA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
32.5487503, -84.7399283
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
600 MW
Source record updated
2026-09-10

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Columbus Council voted 6-2 to create a technology overlay district in the Unified Development Ordinance. A separate rezoning request for the site has not been submitted, and a DRI review is still required.

    Underlying source

Source notes

865 acres in northeast Muscogee County (Upatoi), $5.18 billion, 600 MW — a draw exceeding current power usage for all of Columbus. Columbus Water Works is named as the treated-water supplier. The overlay-district vote is a zoning tool, not project approval. Coordinates are approximate to Upatoi.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory