SOURCE-LINKED U.S. REGISTRY

Prologis Project Mila

Prologis · Trenton, OH · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
39.48, -84.4638
Serving utility, source-reported
Duke Energy Ohio
Operational capacity, source-reported
Not published
Planned capacity, source-reported
250 MW
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    Trenton planning commission unanimously approved Prologis 'Project Mila' (4 × 220k sq ft buildings + on-site substation) in March 2026; construction from fall 2026

    Underlying source

Source notes

Project Mila in Trenton, Butler County (outside Cincinnati): four 220,000 sq ft single-story buildings (880k sq ft total) plus an on-site substation. Planning approved March 2026; construction from fall 2026. Local reporting in 2026 (Journal-News, WYSO) describes a 250-megawatt data center, recorded as planned capacity. Prologis estimates the project will create 120 full-time jobs by December 31, 2035 (Journal-News, WYSO); as an estimate, it is not recorded as a job count. Distinct from Prologis's Newnan, GA campus. Coordinates are the Trenton area centroid.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory