SOURCE-LINKED U.S. REGISTRY

Project Sail – Prologis Data Center Campus

Prologis · Newnan, GA · United States

Facility record

Lifecycle
PermittedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
33.3807, -84.7974
Serving utility, source-reported
Georgia Power
Operational capacity, source-reported
Not published
Planned capacity, source-reported
900 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Prologis acquired site from original developer Atlas Development LLC; DRI review completed February 2024 for 200-acre precursor Pegasus proposal

  2. Permitted

    Coweta County Board of Commissioners approved rezoning 3-2 for 800+ acres along US-27 near Newnan

    Underlying source
  3. Permitted

    Coweta County residents filed appeal in Superior Court seeking to reverse rezoning decision

    Underlying source

Source notes

Nine buildings, 4.3 million sq ft. End tenant not publicly identified; project marketed to hyperscalers. Rezoning includes decommissioning and site restoration plan requirement if dormant over one year. Coordinates are Newnan city centroid; actual site is along US-27 southwest of Newnan. A developer-commissioned fiscal study modeled roughly $488M in county and school property-tax abatements over 18 years, but the Coweta County Development Authority reported no incentive negotiations had occurred as of January 2025; no confirmed incentive agreement or job count has been published.

Georgia Power is the service-territory utility for Coweta County; the site is adjacent to Georgia Power's Plant Yates, and the developer states the load was included in Georgia Power's 2025 Integrated Resource Plan. Reporting indicates Georgia Power was not yet under contract to serve the campus as of mid-2026. No on-site generation reported.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.