QTS Eagle Mountain Data Center Campus
QTS Data Centers · Eagle Mountain, UT · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 40.3155, -111.9847
- Serving utility, source-reported
- Rocky Mountain Power (PacifiCorp)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 200 MW
- Source record updated
- 2026-10-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Permitted
City of Eagle Mountain approved construction; 193-acre campus adjacent to Meta campus
Underlying source - Under construction
Construction initially paused, then restarted; 3 buildings ranging 579,000–592,000 sq ft; water-free cooling system
Underlying source
Source notes
Groundbreaking was October 2025; the third of three initial buildings topped out (structural completion) on 2026-04-20. Not yet operational; no delivery date confirmed.
Grid-served by Rocky Mountain Power. After the utility initially could not guarantee sufficient grid power, the city approved on-site gas turbines and a separate 200 MW gas plant as options, but QTS ultimately secured grid supply. QTS declines to disclose the campus's power capacity (third-party trackers estimate over 650 MW at full build-out); it reports portfolio-wide carbon-free electricity for 2024.
Sources and provenance
- QTS begins construction on new datacenter campus in Eagle Mountain — Eagle Mountain City · source retrieved 2026-07-05
- Eagle Mountain 193-acre data center campus set to be done this year — Utah News Dispatch · source retrieved 2026-07-05
- QTS Eagle Mountain — official data center page · source retrieved 2026-07-06
- Eagle Mountain RDA — Sweetwater #3 CRA / QTS participation agreement (Aug 2024 packet) · source retrieved 2026-07-06
- Questions grow over water use at massive QTS Data Center in Eagle Mountain — KUTV · source retrieved 2026-07-06
- To power Utah's data center boom, companies are turning to fossil fuels — Grist · source retrieved 2026-08-16
- Layton Construction, QTS Data Centers Break Ground on Eagle Mountain Campus · source retrieved 2026-08-08
- Utah's massive data centers seek to build new power sources · source retrieved 2026-10-13
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.