QTS Bessemer (Project Marvel)
QTS Data Centers · Bessemer, AL · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 33.44, -86.97
- Serving utility, source-reported
- Alabama Power
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 1200 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Project Marvel first surfaced March 2025; unnamed developer (via Logistics Land Investment LLC, an affiliate of Atlanta-based TPA Group) sought rezoning of ~700 acres in Bessemer for hyperscale data center
Underlying source - Proposed
Bessemer City Council voted 5-2 to approve rezoning ~700 acres from agricultural (A-1) to light industrial (I-1) on November 18, 2025; developer identity still not publicly disclosed
Underlying source - Proposed
Bessemer City Council approved rezoning of 914 additional acres in April 2026, expanding total site to ~1,607 acres; 18-building count unchanged, additional land used for wider buffers and layout flexibility
Underlying source - Proposed
QTS Data Centers (Blackstone) publicly confirmed as operator behind Project Marvel, July 1-2, 2026; project described as in active planning stage
Underlying source
Source notes
Codename: Project Marvel. 18-building hyperscale campus on Red Ridge near I-459 and I-20/59 interchange in Bessemer (Jefferson County). Announced capacity: up to 1,200 MW at full build-out — reported as a planned ceiling, roughly 9% of Alabama Power's current generating capacity; recorded as a planned capacity of 1,200 MW (an announced 'up to' full-build-out ceiling, consistent with how the dataset records other announced full-build-out figures). Investment: TPA Group's Adam Rashid told the Bessemer City Council in November 2025 that the overall capital investment is expected to be $14.5 billion (WBRC), and that figure is recorded as the investment figure; other reports put it at about $14–14.4B (Logistics Land Investment anticipated 'close to $14.4B'; DCD reported ~$14B), and QTS's own July 2026 statement gives no dollar amount. Land: ~1,607.42 acres total after two rezoning rounds (initial ~700 acres November 2025 + 914-acre expansion April 2026). QTS affiliate purchased land from TPA Group affiliate for $431.73M. Chapter 9B statutory eligibility would have provided a 30-year abatement estimated at $500M+; QTS committed not to seek local property tax incentives (per WBRC July 2026) — no subsidy is recorded, as eligibility does not equal award and QTS renounced pursuit. Full buildout timeline: 7+ years. Birmingham Business Alliance estimated ~$4B net benefit over 30 years; Bessemer City Schools projected ~$25M/year. AI framing not officially confirmed by QTS or the city as of July 2026 — size and scale (hyperscale, cloud/AI demand framing in QTS statement) support an AI classification of likely. Coordinates are approximate for the Red Ridge parcel area. Jobs: ~1,000 construction and ~330 permanent are projected figures for the proposed (not-yet-built) campus (WBRC, Nov 2025), and are recorded as the construction and permanent jobs figures. QTS Data Centers is owned by Blackstone (2021 take-private). Status: Bessemer approved land-use rezonings for this campus in November 2025 and again (914 acres) in April 2026, which, if a rezoning approval is treated as permitted, could argue for permitted rather than proposed. Status is kept at proposed because the cited source dated 2026-07-02 postdates both rezonings and still describes the campus as proposed, and no building permit or site-preparation start was found in any cited source.
Alabama Power confirmed 1,200 MW power availability for the campus. QTS committed project-related energy costs will not be passed on to local utility ratepayers. Opponents (NAACP, Black Warrior Riverkeeper, SELC) raised concerns that the facility will rely on fossil fuels. Bibb County residents identified as potentially facing higher power bills due to grid strain.
Sources and provenance
- QTS confirms plans for proposed data center campus in Bessemer · source retrieved 2026-10-18
- Purported Developer of $14bn Project Marvel Data Center in Bessemer Unveiled as QTS · source retrieved 2026-07-07
- Bessemer City Council approves data center project despite transparency concerns (November 2025) · source retrieved 2026-09-09
- Bessemer approves rezoning of 914 acres for Project Marvel data center · source retrieved 2026-07-07
- Alabama's planned $14bn Project Marvel data center could double in size · source retrieved 2026-07-07
- QTS Data Centers behind Bessemer Project Marvel plans · source retrieved 2026-09-09
- How Will Project Marvel Affect Bessemer And Surrounding Areas? · source retrieved 2026-07-07
- Bessemer Residents Are Speaking Out Against AI Data Center Development · source retrieved 2026-07-07