Sequitor Edge Rapid City

Sequitor Edge · Rapid City, SD · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
S Highway 79, Black Hills Industrial Center
Coordinates
44.0222987, -103.1914102
Serving utility, source-reported
Black Hills Energy
Operational capacity, source-reported
Not published
Planned capacity, source-reported
2 MW
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

Capacity figures differ between sources: Baxtel states an initial 2MW phase scaling to 10MW, and The Rapid City Post (February 2026) reports Sequitor Edge's Victoria Blatchford as saying the initial buildout, one data hall, will require up to 2 megawatts, scaling up to a maximum of 10 megawatts if five data halls are eventually constructed; KOTA TV separately reports 15MW for the same project (also citing a 1.3 PUE design target vs. an industry average of 1.8-2.0). The initial 2MW phase is recorded as planned capacity; the 10MW maximum and KOTA TV's 15MW are not. Tier 3 edge computing facility, greenfield, an initial ~30,000 sq ft building on a 1-acre footprint within a 10-acre site, expandable to five data halls across 7 acres. Construction was reported (by Baxtel and KOTA TV) to begin late summer 2026 with a roughly 14-month build targeting a 2027 opening; none of the sources checked (as of 2026-09-13) confirms construction has actually started. Coordinate is an OSM Nominatim road-level geocode of S Highway 79, Rapid City -- not a confirmed parcel.

Reported to require no new grid infrastructure for the initial phase.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.