Serverfarm ARK Clarksville Data Center Campus
Serverfarm · Clarksville, AR · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 35.4673307, -93.4405664
- Serving utility, source-reported
- Clarksville Connected Utilities
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 432 MW
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Serverfarm affiliate SF ARK1 LLC acquired two parcels totaling 135 acres just north of Clarksville's water treatment plant on Palmer Road; land was rezoned from rural to industrial. Five buildings in three phases were then planned, with the tenant company undisclosed.
Underlying source - Under construction
The Arkansas Advocate reported in July 2026 that construction at the Serverfarm site near Johnson Regional Medical Center began earlier that year. Serverfarm's own site says it plans to complete the first two buildings by January 2028.
Underlying source
Source notes
Coordinates are an OpenStreetMap geocode of Palmer Road in Clarksville, the road the Arkansas Democrat-Gazette identifies as the site's location ('just north of the city's water treatment plant on Palmer Road'); this is a road-level approximation, not a parcel-confirmed footprint. Reported figures diverge across sources and are not reconciled: acreage is reported as two parcels totaling 135 acres at acquisition (Nov. 2025), and a later, larger campus figure appears only in subscriber-only reporting that is not cited, so as of October 2026 no land area is recorded; investment is reported as 'at least one billion' (Nov. 2025), $6.6 billion (2026 reporting and Serverfarm's own page) and $8 billion (Arkansas Advocate, May 2026); building count is reported as four (Serverfarm's own page), five (Nov. 2025) and six (trade press). Building size is given as 300,000 sq ft each by Serverfarm and 360,000 sq ft each in trade press. The recorded investment figure is $6.6 billion, as stated on Serverfarm's own page. The Arkansas Democrat-Gazette (Nov. 2025) reports that Serverfarm is owned by Manulife Investment Management.
Serverfarm's own campus page says natural gas is used to support the project in the short term, with a goal of transitioning off gas and adding renewable energy later. Arkansas Democrat-Gazette headlines of August and October 2026 report that the campus plan includes 40 natural gas turbines and that the planned turbines were OK'd by the Arkansas Division of Environmental Quality; the article text is subscriber-only and is not cited for turbine ratings or other details, so as of October 2026 no on-site generation capacity is recorded. As of September 2026, the on-site generation plant is tracked separately as Serverfarm Clarksville Campus On-Site Gas Turbine Plant.
Sources and provenance
- Clarksville's data center plan includes 40 natural gas turbines · source retrieved 2026-09-15
- ARK - Clarksville Arkansas Data Center Campus · source retrieved 2026-09-15
- Data center builder preparing $1 billion project in Clarksville · source retrieved 2026-09-15
- Mixed opinions, limited information about $6.6 billion data center in Arkansas River Valley (Arkansas Advocate reprint) · source retrieved 2026-09-15
- OpenStreetMap Nominatim geocode: Palmer Road, Clarksville, Johnson County, Arkansas · source retrieved 2026-09-15
- Clarksville data center's planned 40 gas turbines OK'd by Arkansas Division of Environmental Quality · source retrieved 2026-10-18
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.