Servistar Realties Westfield Data Center Campus
Servistar Realties · Westfield, MA · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Servistar Industrial Way
- Coordinates
- 42.157077, -72.741619
- Serving utility, source-reported
- City of Westfield
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 42 MW
- Source record updated
- 2026-10-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Local approval 2021, tax exemption law 2024
Underlying source - Cancelled
Westfield Planning Board voted unanimously (Oct 13, 2026) to deny an extension of Servistar's special permit, which expires at the end of October 2026. The developer never bought the land, and its LLC was administratively dissolved. Servistar had 20 days to appeal.
Underlying source
Source notes
Would-be first Massachusetts hyperscale data center: 10-building, 2.7M sq ft campus over a long buildout (191/199 Servistar Industrial Way). Tax exemption secured 2024. Status is early and thin — no confirmed groundbreaking; conflicting signals on whether the project is still active.
Servistar said it would be an 'Independent Customer' of Westfield Gas & Electric. WG&E's general manager estimated the interconnection study and substation work would take about five years. The Shoestring reported that the approved 10-building plan was expected to carry 18 to 42 MW of critical IT load.
Sources and provenance
- Westfield Data Center Campus · source retrieved 2026-10-06
- Massive, multi-billion-dollar data center campus planned in western Massachusetts · source retrieved 2026-07-17
- Ban, ban, ban: data center discontent reaches western Massachusetts · source retrieved 2026-10-24
- Data centers, AI, and Massachusetts towns · source retrieved 2026-07-17
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- The Reminder (Hampden County) · source retrieved 2026-07-26
- Pioneer Valley communities rally against data centers · source retrieved 2026-10-24
- Council approves tax break for data center project · source retrieved 2026-10-24
- Westfield planning board kills $3 billion data center project · source retrieved 2026-10-24
- Westfield planning board denies permit extension for hyperscale data center project · source retrieved 2026-10-24
- Westfield planning board kills $3 billion data center project · source retrieved 2026-10-24