Servpac MTP Building 2
Servpac · Mililani, HI · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 21.448, -158.017
- Serving utility, source-reported
- Hawaiian Electric Company (HECO)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-30
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Servpac announced MTP Building 2 expansion at Mililani Technology Park; $13M investment planned to approximately 10x existing 1MW IT capacity of Building 1; as of February 2026 reporting, project was in design phase with construction details not yet disclosed
Underlying source - Under construction
Servpac held the groundbreaking ceremony for MTP Data Center Building 2 on 2026-01-22. Its own release, the PR Newswire distribution (2026-02-24) and Building Industry Hawaii (March 2026) all report it. Building 2 is a 15,500+ sq ft, $13M building on an additional 5 acres of company-owned land, with Ralph S. Inouye Co. as general contractor. Completion was targeted for Q2 2026, but no completion or opening announcement was found as of 2026-10-02, so under construction is the current sourced state.
Underlying source
Source notes
Located in Mililani Technology Park, Central O'ahu, 10 miles inland and 850 feet above sea level, outside major flood, tsunami, and hurricane zones. Building 2 will approximately 10x the existing 1MW IT capacity of MTP Building 1 (Hawaii's only Uptime Institute Tier IV certified facility). Designed to withstand Category 5 hurricane-force winds. Primary use is enterprise colocation; no AI-specific tenant announced. DCD (February 2026) reports project is in design phase; 'broke ground' claim in original record is unsupported by the cited source. Hawaii's structural barriers (highest US electricity costs, limited grid capacity) make large-scale hyperscale AI builds unlikely; Servpac MTP2 is the only Hawaii project of note found.
Grid power supplemented by on-site solar (500 solar panels generating approximately 1MWh of energy daily per DCD source — capacity is well below 1MW). Independent power and cooling systems capable of operating if commercial power fails.
Sources and provenance
- Hawaii-Based Cloud Provider Servpac Expands Data Center · source retrieved 2026-07-06
- Servpac's MTP Data Center Celebrates Groundbreaking for Building 2 · source retrieved 2026-10-02
- Hawaii Tier IV Data Center: MTP Building 2 Groundbreaking · source retrieved 2026-10-02
- Servpac Inc. breaks ground on MTP Data Center's Building 2 · source retrieved 2026-10-02
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.