SOURCE-LINKED U.S. REGISTRY

STACK Infrastructure Goldendale Data Center

STACK Infrastructure · Goldendale, WA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
45.8213, -120.8217
Serving utility, source-reported
Klickitat PUD
Operational capacity, source-reported
Not published
Planned capacity, source-reported
958 MW
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

Identified via a 2022 Puget Sound Energy interconnection filing describing a 958MW STACK data center in 'study phase,' sited on a portion of a 700-acre former aluminum smelter (ex-Lockheed Martin) near the John Day Dam. STACK has not publicly confirmed its involvement.

958 MW per the 2022 load connection request between Klickitat PUD and BPA, which names IPI and STACK. Build-out is expected in small increments. The only Klickitat request with a formal BPA agreement covers 160 MW of transmission capacity. No power source is lined up yet and the developer would pay for upgrades.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.