SOURCE-LINKED U.S. REGISTRY

Stargate Lordstown Campus

OpenAI / SoftBank / Oracle · Lordstown, OH · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41.1745, -80.8534
Serving utility, source-reported
FirstEnergy (Ohio Edison)
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-10-30

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Under construction

    Ground broken; using former Lordstown Motors / GM assembly plant; modular prefab data center approach

    Underlying source
  2. Proposed

    One of five new Stargate sites; SoftBank investing $3B to convert former GM EV plant into modular AI data center factory

    Underlying source
  3. Under construction

    Epoch AI satellite imagery: "Active construction visible on and around the datacenter, with the roofing mostly in place." Epoch AI reports no buildings operational yet.

    Underlying source

Source notes

No capacity is recorded for this site alone: the September 2025 announcement said Lordstown and Milam County together "can scale to 1.5 gigawatts over the next 18 months," and gave no Lordstown-only figure. A SoftBank spokesperson said the initial SoftBank/OpenAI data center uses "a small part" of the 6.2M-sq-ft site, which also hosts a Foxconn/SoftBank hub manufacturing modular data-center equipment. Crescent Dune LLC (a SoftBank affiliate) acquired the site from Foxconn for $375M (Sept 2025, Trumbull County Auditor). SoftBank's "up to $3 billion" is a ceiling covering both manufacturing and the data center — no data-center-only investment figure is confirmed.

Lordstown sits in FirstEnergy/Ohio Edison territory (eastern PJM); sources cite "affordable electricity from FirstEnergy and American Electric Power" and FirstEnergy's high-voltage transmission. FirstEnergy completed a $30M grid upgrade (2019–2022) anticipating large industrial load. On-site generation for the data center is not confirmed in site-specific filings; the adjacent, independently owned Lordstown Energy Center is a separate gas plant.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.