Project Horizon (Tech oNE Crossing)
Starwood Digital Ventures · Kearney, NE · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 40.728341, -99.045806
- Serving utility, source-reported
- Nebraska Public Power District
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 368 MW
- Source record updated
- 2026-10-12
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Kearney Planning Commission unanimously recommended a conditional use permit for Project Horizon at Tech oNE Crossing; applicant Worldwide Mission Critical, with Starwood Digital Ventures (SDV) partnering with MARA.
Underlying source - Permitted
Kearney City Council unanimously approved the Project Horizon conditional use permit.
Underlying source
Source notes
Multi-phase data center campus at Tech oNE Crossing, east of Antelope Ave. and south of Tech One Blvd/Global Drive, outside Kearney city limits. 368 MW total electrical demand at full build-out. Phase 1 reuses the 100 MW of capacity at the adjacent existing crypto-mining site, which is to be decommissioned after Phase 1; Phase 3 extends onto the former mining property. That mining site is tracked separately as the MARA Kearney Facility as of October 2026; this record is the successor AI/data-center campus, not a duplicate of it. WOWT (carrying a Flatwater Free Press report) says the city acquired roughly 112 acres for the Tech oNE tech park as a whole; as of October 2026, that report gives no acreage for the campus itself. It reports first phase completion by late 2027 and full capacity around 2030; the tenant is undisclosed under NDA. Permit conditions: development must begin within two years, plus annual hazardous-materials inventory. Coordinates are approximate, borrowed from the adjacent mining site on the same Tech oNE Crossing parcel complex.
Phase 1 reuses 100 MW of existing capacity at the site's crypto-mining operation; SDV said it would pay for any infrastructure upgrades needed for the added demand.
Sources and provenance
- Kearney Planning Commission recommends approval of proposed data center · source retrieved 2026-10-12
- Project Horizon data center CUP recommended by Kearney Planning Commission (368 MW, three phases) · source retrieved 2026-10-12
- Kearney City Council unanimously approves Project Horizon data center · source retrieved 2026-10-12
- Kearney poised to go all in on data centers even as many Nebraska towns throttle back · source retrieved 2026-10-12
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.