T5 @ Atlanta IV

T5 Data Centers · Palmetto, GA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Weldon Road at Palmetto-Tyrone Road
Coordinates
33.548, -84.724
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
300 MW
Source record updated
2026-10-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Land acquisition finalized; 91-acre site already zoned for data-center use; use permit still required

    Underlying source
  2. Proposed

    T5 refiled modified plans: 1.32M sq ft, 3 buildings, up to 300 MW; the original June 2024 filing (495K sq ft, 2 buildings) was withdrawn

    Underlying source

Source notes

City discrepancy: the ledger cited Fairburn, but T5's own page and PR Newswire list Palmetto, GA; DCD describes it as Fairburn/Fulton County with a 91-acre site in Palmetto - site is on the Fairburn/Palmetto border in South Fulton County (I-85 and Gullatt Rd). Capacity: T5's page lists '200 MW available' (Phase 1) while the Aug 2024 land-acquisition PR cites '300 MW' campus total - 300 MW recorded as planned. No tenant disclosed (T5 is a wholesale/build-to-suit developer targeting hyperscalers; page cites AI/liquid-cooling suitability). Phase 1 construction targeted Q2 2027; on-site substation expected 2026. No jobs figure disclosed as of July 2026. T5 has disclosed no investment figure, so none is recorded. The Newnan Times-Herald reports that Project Pegasus, a 2.95-million-square-foot, seven-building, 200-acre project proposed by T5@Atlanta IV, LP at Weldon and Palmetto-Tyrone roads in Coweta County (regional-impact review completed February 2024), is estimated to be valued at $1.5 billion at buildout; as of October 2026, no source read shows that project is the 91-acre campus described here, so the figure is not recorded. Coordinates approximate (I-85/Gullatt Rd corridor).

On-site electrical substation providing grid power; substation expected operational 2026.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.