Justified Data Campus

TeraWulf · Hawesville, KY · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
37.8999, -86.7569
Serving utility, source-reported
Big Rivers Electric Corporation
Operational capacity, source-reported
Not published
Planned capacity, source-reported
401 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Permitted

    TeraWulf acquired ~750-acre former Century Aluminum smelter site from Century Aluminum subsidiary; Justified Data campus announced February 2, 2026.

    Underlying source
  2. Under construction

    20-year lease signed with Anthropic PBC (via TeraWulf's Raylan Data LLC entity) for 401 MW critical IT load; ~$19B contracted lease revenue over initial term. Initial capacity targeted H2 2027; full 401 MW ramp by early 2028. Announced July 6, 2026.

    Underlying source

Source notes

Brownfield redevelopment of former Century Aluminum smelter. Site acquired February 2026 from Century Aluminum subsidiary; acquisition price reported by multiple outlets as $200M cash plus a 6.8% minority equity interest in TeraWulf (not confirmed in the official press release text as of July 2026). Lease entity: TeraWulf's Raylan Data LLC to Anthropic PBC. The ~$19B is contracted lease revenue over the 20-year term — not capex; not recorded as an investment figure. TeraWulf indicated a $3B–$4B construction investment for two data center buildings (range, not a firm single figure; not recorded as an investment figure). Site has ~480 MW of existing power availability; 401 MW is the Anthropic lease capacity. Total site ~750 acres per news sources; TeraWulf's official PR cited 'over 250 buildable acres.' Coordinates are approximate (Hawesville town center). The Fluidstack/Abernathy JV is a separate unrelated transaction and is not part of this record.

Site connects directly to regional transmission network via on-site energized substation and multiple high-voltage transmission lines, bypassing local distribution. Big Rivers Electric filed a retail service agreement with the Kentucky PSC in April 2026 covering 482 MW transmission capacity for the Justified Data project; TeraWulf bears identified costs and risks for obtaining and transmitting capacity. TeraWulf is covering the full cost of required grid upgrades.