Justified Data Campus
TeraWulf · Hawesville, KY · United States
Facility record
- Lifecycle
- Under constructionSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 37.8999, -86.7569
- Serving utility, source-reported
- Big Rivers Electric Corporation
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 401 MW
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Permitted
TeraWulf acquired ~750-acre former Century Aluminum smelter site from Century Aluminum subsidiary; Justified Data campus announced February 2, 2026.
Underlying source - Under construction
20-year lease signed with Anthropic PBC (via TeraWulf's Raylan Data LLC entity) for 401 MW critical IT load; ~$19B contracted lease revenue over initial term. Initial capacity targeted H2 2027; full 401 MW ramp by early 2028. Announced July 6, 2026.
Underlying source
Source notes
Brownfield redevelopment of former Century Aluminum smelter. Site acquired February 2026 from Century Aluminum subsidiary; acquisition price reported by multiple outlets as $200M cash plus a 6.8% minority equity interest in TeraWulf (not confirmed in the official press release text as of July 2026). Lease entity: TeraWulf's Raylan Data LLC to Anthropic PBC. The ~$19B is contracted lease revenue over the 20-year term — not capex; not recorded as an investment figure. TeraWulf indicated a $3B–$4B construction investment for two data center buildings (range, not a firm single figure; not recorded as an investment figure). Site has ~480 MW of existing power availability; 401 MW is the Anthropic lease capacity. Total site ~750 acres per news sources; TeraWulf's official PR cited 'over 250 buildable acres.' Coordinates are approximate (Hawesville town center). The Fluidstack/Abernathy JV is a separate unrelated transaction and is not part of this record.
Site connects directly to regional transmission network via on-site energized substation and multiple high-voltage transmission lines, bypassing local distribution. Big Rivers Electric filed a retail service agreement with the Kentucky PSC in April 2026 covering 482 MW transmission capacity for the Justified Data project; TeraWulf bears identified costs and risks for obtaining and transmitting capacity. TeraWulf is covering the full cost of required grid upgrades.
Sources and provenance
- TeraWulf Announces Anthropic Lease at Justified Data Campus · source retrieved 2026-07-07
- TeraWulf Announces Anthropic Lease at Justified Data Campus (GlobeNewswire) · source retrieved 2026-07-07
- TeraWulf Expands Digital and Power Infrastructure Portfolio — Kentucky and Maryland Acquisitions · source retrieved 2026-07-07
- TeraWulf Expands Digital and Power Infrastructure Portfolio (GlobeNewswire, Feb 2026) · source retrieved 2026-07-07
- Big Rivers Electric Corporation — PSC Retail Service Agreement Filing for Justified Data Project · source retrieved 2026-07-07
- Hawesville smelter to become AI data center; community split on economic impact · source retrieved 2026-07-07
- TeraWulf signs 20-year Anthropic lease for 401 MW at Kentucky data campus · source retrieved 2026-07-07
- Anthropic signs $19bn, 20-year lease for Kentucky data center with TeraWulf · source retrieved 2026-07-07
- AI company Anthropic commits to long-term Hawesville campus · source retrieved 2026-07-07
- Construction Dive — Terawulf taps Fluor for preconstruction on $3B Kentucky data center · source retrieved 2026-07-25
- Kentucky PSC Approves 482 MW Power Agreement for TeraWulf's Justified Data Campus · source retrieved 2026-09-15
- Data centers need massive power. They're eyeing Kentucky's idle industrial sites to get it. (Century Aluminum smelter site, Hancock County, 482 MW, wholesale power via the MISO market) · source retrieved 2026-09-15
- Big Rivers Electric Corporation filing: Justified DataPower LLC / TeraWulf Inc. Retail Electric Service Agreement, PSC Case 2026-00115 (April 14, 2026) · source retrieved 2026-09-22
- Kentucky PSC Approves 482 MW Power Agreement for TeraWulf's Justified Data Campus · source retrieved 2026-09-22
- KY utility regulator OKs electricity contract for TeraWulf's Hancock County data center project · source retrieved 2026-10-22
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.