TeraWulf Muskie Data Campus (EastPark)
TeraWulf · Ashland, KY · United States
Facility record
- Lifecycle
- ProposedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 38.4042, -82.79
- Serving utility, source-reported
- Kentucky Power (AEP)
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 1000 MW
- Source record updated
- 2026-10-28
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
TeraWulf announced the acquisition of the 285-acre Muskie Data Campus from Industrial Equity Partners at EastPark Industrial Park; land purchase closed effective 2026-05-22
Underlying source
Source notes
TeraWulf's second Kentucky campus (alongside the Justified/Hawesville campus, tracked separately as of July 2026). TeraWulf (Nasdaq: WULF), historically a bitcoin miner, repositioning toward HPC/AI. Muskie is a 285-acre site at EastPark Industrial Park (a 1,000-acre former strip mine). Planned 1+ GW phased: initial 500 MW ramp H2 2028, additional 500 MW targeted H2 2030. County discrepancy: local TV cites Boyd County, but Wikipedia places EastPark at the junction of Boyd, Greenup and Carter counties, with most of the park in Greenup County; Greenup used, city Ashland retained as the regional reference. Investment omitted: the $4B figure came from a Boyd County official, not TeraWulf's investor PR or 8-K. Sources give different long-term job figures: a WCHS report cites around 300 long-term positions, while TeraWulf told a community meeting reported by the Herald-Dispatch that it expects to employ up to 100 workers once the campus is online, with tenants possibly creating about 100 more jobs; both are estimates or ceilings, so no permanent job count is recorded. TeraWulf stated it will pay the full standard industrial tariff with no subsidies. Coordinates are the EastPark park centroid.
Kentucky Power (an AEP company) is building a 345 kV substation on the existing 765 kV network to serve the campus. TeraWulf confirmed it will pay the full Industrial General Service tariff with no discounts or exemptions. Phased power: 500 MW H2 2028, +500 MW H2 2030.
Sources and provenance
- New AI data center coming to eastern Kentucky · source retrieved 2026-07-07
- TeraWulf Expands Infrastructure Platform with Acquisition of 1+ GW Eastern Kentucky HPC Campus · source retrieved 2026-09-15
- Massive new data center project announced in northeastern Kentucky · source retrieved 2026-07-07
- New data center project announced in northeastern Kentucky · source retrieved 2026-07-07
- Boyd County leaders on the economic impact of the proposed data center · source retrieved 2026-07-07
- EastPark, Kentucky - Wikipedia · source retrieved 2026-07-07
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- Herald-Dispatch — TeraWulf details data center planned for east Kentucky · source retrieved 2026-07-25
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.