Thor Equities Augusta Township Data Center (Form8tion)
Thor Equities · Augusta Township, MI · United States
Facility record
- Lifecycle
- CancelledSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 42.163, -83.72
- Serving utility, source-reported
- DTE Energy
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-22
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Thor Equities (via Form8tion / JDS Equities II LLC) acquires 810 acres in Augusta Township; seeks rezoning of 522 acres from agricultural/residential to General Industrial
Underlying source - Proposed
Augusta Township Planning Commission recommends denial 5-1, citing inconsistency with land-use plans
Underlying source - Proposed
Augusta Township Board of Trustees unanimously approves rezoning of 522 acres despite Planning Commission denial
Underlying source - Proposed
Residents collect 957 signatures for ballot initiative (threshold was 561); question set for 2026 ballot (May or August primary election) to overturn rezoning
Underlying source - Cancelled
Augusta Township voters overturned the rezoning at the August primary — about 90% voted to overturn — returning the seven parcels to agricultural residential and removing the zoning the project depended on. Results were still unofficial as of 2026-08-05.
Underlying source
Source notes
Site north of Milan-Oakville Road, east of Hitchingham Road, Augusta Township, Washtenaw County MI (between Ann Arbor and Monroe). No end user announced; planners cited Google and Microsoft as typical users of this facility type. Form8tion is Thor's digital infrastructure arm (founded March 2023). Capacity not disclosed; at least five large buildings planned. Coordinates are approximate Augusta Township centroid. Augusta Township voters overturned the 522-acre rezoning on 2026-08-04 (about 90% to overturn), so the parcels revert to agricultural residential. Recorded as cancelled because the project's enabling rezoning is gone; Thor Equities has not publicly withdrawn, and the results were unofficial as of 2026-08-05. The cancelled status dated 2026-08-04 corresponds to the Aug. 4 veto referendum on the 522-acre rezoning, and as of September 2026 nothing found indicates a revival, appeal or re-rezoning since. As of October 2026, no cited source gives certified vote totals, so the date and mechanism are confirmed but not the tally.
Sources and provenance
- Local officials recommend denial of Thor Equities data center in Michigan · source retrieved 2026-07-06
- Can 957 signatures halt a $1 billion data center in Augusta Township? · source retrieved 2026-07-06
- Tiny Michigan town hopes to stop data center with ballot initiative · source retrieved 2026-07-06
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · source retrieved 2026-07-23
- Augusta Township data center battle reaches the ballot — 522 acres, agricultural residential to general industrial, vote set for 2026-08-04 · source retrieved 2026-08-08
- Augusta Township voters overturn data center rezoning — “about 90% of voters chose to overturn” · source retrieved 2026-08-08