Townsite Solar 2 Boulder City Data Center
Townsite Solar 2 LLC · Boulder City, NV · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 35.9787649, -114.8337574
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- 167 MW
- Source record updated
- 2026-09-24
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Townsite Solar 2 withdrew its application to build on approximately 88.5 acres of Boulder City-owned land; reporting indicates the developer intends to pursue a nearby federally owned parcel instead.
Underlying source - Permitted
The Bureau of Land Management approved the Townsite Data Center in June 2026 on 88.5 acres of federal land in Eldorado Valley inside Boulder City limits — reported as the first data center ever approved on public lands. The approval stands but is currently stayed: on 2026-09-01 the Interior Board of Land Appeals granted a stay halting construction pending administrative appeal, finding BLM likely violated environmental law by reusing the 2023 environmental review of a 19 MW solar project on the same site. BLM's administrative record was due 2026-09-21 with expedited briefing to follow. Separately, TS2 withdrew its application for the adjacent city-owned site on 2026-07-06.
Underlying source
Source notes
Proposed as two warehouse-style server buildings plus a 230 kV substation, battery energy storage and perimeter fencing, maximum 40-foot height with dark-sky-compliant lighting. The city page states 200-300 construction/testing jobs and 25-40 permanent technical positions; these ranges are not recorded as point values in the jobs field. Reported as a joint venture of Skylar Capital, Arevon Energy and Overwatch Capital, but that ownership was read only in a search summary and is not asserted here. Status is kept at proposed rather than cancelled: the withdrawal was of the city-land application, not of the project.
Self-supplied through a dedicated project-funded 230 kV line from the Mead substation, completely separate from Boulder City's power distribution system, with on-site battery storage for peak management. Peak demand stated as 167 MW, under 2% of Mead substation capacity.
Sources and provenance
- TS2 Data Center Proposal (withdrawn 7.6.2026) - official Boulder City project page · source retrieved 2026-08-29
- Data centers in Nevada - project list (Townsite Solar 2 Boulder City Data Center, Clark County, 170 MW, planned) · source retrieved 2026-08-29
- IBLA 2026-0213 / IBLA 2026-0216 stay order (Sept. 1, 2026) - City of Boulder City and Center for Biological Diversity v. BLM, Townsite Data Center amended right-of-way · source retrieved 2026-09-11
- Nevada city dubs itself a test case for data centers on federal lands near communities - 81-acre BLM parcel in Eldorado Valley, BLM approval released June 26 · source retrieved 2026-09-11
- Federal Board Halts 167-MW Nevada Data Center Approval · source retrieved 2026-09-24
- Appeal Challenges Public Lands Data Center in Nevada · source retrieved 2026-09-24
- Data Centers — Boulder City official page (TS2 city-site application withdrawn 2026-07-06) · source retrieved 2026-09-24
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.