Cannon Falls Technology Park (Tract)
Tract · Cannon Falls, MN · United States
Facility record
- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 44.5068445, -92.9062175
- Serving utility, source-reported
- Dakota Electric Association
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-13
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
City annexed about 240 acres between Rochester Blvd and Hwy 52 from Randolph Township for the Tract project
Underlying source - Permitted
Council voted 4-2 to approve the CUP and development agreement, rezoning to general industrial
Underlying source
Source notes
The site lies just north of Cannon Falls, between Highway 52 and Rochester Blvd, on land annexed from Randolph Township. Reported acreage is about 240 to 250+ acres. The pin is the city centroid because no parcel point was sourced. The Post Bulletin article (Nov 6, 2025) says the vote was 'Wednesday', inferred as Nov 5, 2025. Investment figures conflict ('$30 billion over 20 years' per KSTP versus 'hundreds of millions to potentially a billion' per KTTC), so investment is omitted.
Dakota Electric will serve the project. Tract would fund and build an on-site substation.
Sources and provenance
- Cannon Falls City Council approves permits for data center project · source retrieved 2026-10-13
- Cannon Falls, Pine Island are both discussing bringing data centers to their towns · source retrieved 2026-10-13
- Cannon Falls explores major data center project following land annexation · source retrieved 2026-10-13