ValorC3 Saint George Data Center
ValorC3 · St. George, UT · United States
Facility record
- Lifecycle
- OperationalSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 37.10988, -113.58321
- Serving utility, source-reported
- Not established
- Operational capacity, source-reported
- 4 MW
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-11-02
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.
Source notes
Subsidies checked at the municipal tier (2026-09-08): no site-level subsidy found. St. George's FY2025-26 Redevelopment Agency budget itemizes every currently active project area by name (Central Business District CDA, Dixie Center EDA, Ft. Pierce CDA #1, Ft. Pierce CDA #2, Millcreek CDA, and Tech Ridge CDA — formerly the St. George Airport Community Development Project Area), none covering the Tonaquint corridor at 1108 West 1600 South; the facility instead sits within Tonaquint Business Park, a privately developed park built by the site's own developer to attract tech companies, not a public redevelopment district. No city or state filing names Valor C3. Utah's EDTIF programme excludes data centres and the UCA 59-12-104 sales-tax exemption is self-executing.
Sources and provenance
- Data Center Growth in Utah and the United States — Data Summary, April 2026 (tables: Operating Data Centers in Utah, March 2026; Planned Data Centers in Utah, March 2026) · source retrieved 2026-08-14
- St. George Redevelopment Agency FY2025-26 budget agenda packet — itemizes all six currently active project areas by fund number and name · source retrieved 2026-09-08
- New data center project in Utah — the facility was built by Kay Traveller of Tonaquint Development on land within the privately developed Tonaquint Business Park · source retrieved 2026-09-08
- Kem C. Gardner Policy Institute, Data Center Growth in Utah (April 2026), Operating Data Centers table · source retrieved 2026-11-02
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.