SOURCE-LINKED U.S. REGISTRY

Vantage Data Centers OH2 (Millersport Campus)

Vantage Data Centers · Millersport, OH · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
39.902, -82.5324
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
696 MW
Source record updated
2026-09-10

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

Vantage's second Ohio campus (distinct from the tracked OH1 in Johnstown), at Lancaster-Newark Rd & Blacklick Rd near Millersport — up to 7 structures incl. 4 data-center buildings, $2.1B, powered by an adjacent natural-gas generation facility; under construction as of mid-2026. Capacity figures diverge: 696 MW on Vantage's own site (used here) vs ~800 MW / 500 acres on a project aggregator — the operator figure is used and the discrepancy flagged. Coordinates approximate (Millersport city-center, not parcel-verified). Public-reception check (2026-09-10): Checked the project's own campus microsite (2026-09-10); it covers only project description and planned economic benefits, with no documented public hearing, resident reaction, or official statement of support/opposition.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.