SOURCE-LINKED U.S. REGISTRY

Vantage Wyoming Campus (Project Latigo)

Vantage Data Centers · Cheyenne, WY · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
41, -104.89
Serving utility, source-reported
Black Hills Energy
Operational capacity, source-reported
Not published
Planned capacity, source-reported
480 MW
Source record updated
2026-10-17

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Open house held. Vantage says permitting for the 480 MW project begins in late 2026 and runs into 2027.

    Underlying source

Source notes

About 12 miles south of Cheyenne along Terry Ranch Road. Starts at 480 MW with potential to scale to about 1 GW, in three to five buildings. Reported investment is $4.8B-$9.6B (a range, so it is not entered as a field). The coordinates are approximate, placed from the described Terry Ranch Road / I-25 location and the Cheyenne LEADS map pin. No parcel point was found.

The campus needs a natural gas power plant. Vantage says it will pay to build the plant and to connect it to Black Hills Energy, so residential and small-business customers do not carry those costs.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory