SOURCE-LINKED U.S. REGISTRY

Energy Generation and Technology Campus

W Holdings · Maricopa, AZ · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
32.945, -112.035
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-08-28

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Pinal County Board of Supervisors unanimously approved the major comprehensive plan land-use amendment; rezoning still required.

    Underlying source

Source notes

Located south of the City of Maricopa, east of State Route 347 and west of the Nissan test track, abutting the southern boundary of the Ak-Chin Indian Community. Investment is recorded as the itemized $4B construction plus $5.5B equipment figure presented to the Planning and Zoning Commission; a separate report rounds the total to $10B. Acreage is also reported as 500 and, in one account, 656 acres. Some coverage associates the site with Copia Power; the applicant of record in commission and board coverage is W Holdings, represented by the same attorney who has appeared for Copia projects, so the corporate relationship is not established here.

Plan pairs data centers with an on-site natural gas power plant and battery energy storage. The applicant told the commission the campus would be powered primarily by the Griffin Energy Project (solar, gas and battery). No MW figure has been stated publicly.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory