Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
300 South First Street
Coordinates
37.3314706, -121.8865883
Serving utility, source-reported
Not established
Operational capacity, source-reported
Not published
Planned capacity, source-reported
Not published
Source record updated
2026-09-21

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Planned Development Permit PD25-013 submitted 2024-10-17: a seven-story (two below-grade levels), 200-ft, ~238,000 sq ft data center alongside three 30-story mixed-use towers (1,164 units) on a 2.84-acre site; environmental review under way. San José City Council voted 2025-04-08 to advance Westbank's downtown proposals through the Innovative Project Pathway.

    Underlying source

Source notes

Part of Westbank's downtown San José program pairing data centers with housing; San José Spotlight reports the two downtown sites (300 S. First and 323 Terraine) total 99 MW combined — not attributed to this site alone.