- Lifecycle
- PermittedSource-reported lifecycle
- Location precision
- approximate
- Address as listed
- Not published
- Coordinates
- 37.5154292, -77.73203
- Serving utility, source-reported
- Dominion EnergyView utility impact evidence
- Operational capacity, source-reported
- Not published
- Planned capacity, source-reported
- Not published
- Source record updated
- 2026-10-14
Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.
Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.
Reported lifecycle history
- Proposed
Province Group affiliate LC West LLC sought to rezone 120 acres at the Powhatan–Chesterfield line, including 1318 Page Road.
Underlying source - Permitted
Supervisors voted 3-2 to approve the rezoning and CUP against the Planning Commission's recommendation.
Underlying source - Permitted
An adjacent ~60-acre parcel was rezoned unanimously, forming a 180-acre campus.
Underlying source
Source notes
The original 119.9-acre approval covered three detached data centers of about 1.525M sq ft. The county estimated $2.7B, the developer $3B, with 165 direct jobs (Mangum study). The 60-acre addition makes a 180-acre campus. These investment and job figures refer to the original phase, so they are not set as campus fields. The coordinates are the OSM geocode of 1318 Page Road, one of the three parcels.
A Dominion substation is required. Virginia Business reported about 300 MW at full capacity for the original 119.9-acre approval.
Sources and provenance
- Powhatan green-lights $2.7B data center campus · source retrieved 2026-10-14
- Virginia's Powhatan County greenlights 180-acre data center development · source retrieved 2026-10-14
- Data center project proposed for 120-acre site in Powhatan County · source retrieved 2026-10-14
Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.