SOURCE-LINKED U.S. REGISTRY

Project Q — Quiet Data Centers Enfield (Halifax County)

Quiet Data Centers Halifax Inc. · Enfield, NC · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
36.18, -77.66889
Serving utility, source-reported
DominionView utility impact evidence
Operational capacity, source-reported
Not published
Planned capacity, source-reported
88 MW
Source record updated
2026-09-10

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Halifax County held a special meeting on the conveyance; property closing expected Sept. 18, 2026.

    Underlying source

Source notes

County-owned 251-acre industrial site off Trestle Road near U.S. 301 outside Enfield; the data center campus itself is described as roughly 14–15 acres with a 90,000–100,000 sq ft building. Phase 1 about 38 MW, final about 88 MW. Minimum contractual commitment is a $250M taxable investment and 50 permanent jobs; the company said the eventual investment could approach $1 billion — that larger figure is aspirational, not committed.

Company said electricity would be sourced through Dominion, with the company covering transmission/substation costs and no rate subsidy from residential customers.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.

Back to map & directory