SOURCE-LINKED U.S. REGISTRY

Tuckahoe Technology Park

Tract · , VA · United States

Facility record

Lifecycle
ProposedSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
37.68, -77.68
Serving utility, source-reported
Dominion Energy VirginiaView utility impact evidence
Operational capacity, source-reported
Not published
Planned capacity, source-reported
900 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

No dated operational history is established in this record. Publication, discovery and source-update dates are not opening dates.

Source notes

Eastern Goochland County, west of West Creek Business Park; 13 parcels, up to 7 development areas/buildings. $3B+ construction spending projected over a 5-7 year buildout. Pre-application for a conditional-use permit filed June 10, 2026 - the first project under Goochland's new Technology Overlay District. Coordinates are approximate.

900MW campus proposed to be 'served by multiple on-site substations connected to nearby high-voltage transmission lines' — a standard Dominion Energy grid interconnect. No renewable PPA, on-site generation, or clean-energy commitment disclosed in reporting or the county's project page.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.