SOURCE-LINKED U.S. REGISTRY

Vantage Data Centers VA4 Stafford Campus

Vantage Data Centers · , VA · United States

Facility record

Lifecycle
Under constructionSource-reported lifecycle
Location precision
approximate
Address as listed
Not published
Coordinates
38.44, -77.44
Serving utility, source-reported
Dominion EnergyView utility impact evidence
Operational capacity, source-reported
Not published
Planned capacity, source-reported
192 MW
Source record updated
2026-10-22

Source-reported capacity; not metered consumption. Review underlying documents and notes. Planned capacity may include future phases and is not added to operational capacity here. The source may use facility, grid-feed or IT capacity definitions; consult the linked documents.

Coordinate precision is a source label, not an independent parcel survey. A marker does not confirm utility territory or establish an effect on residential bills.

Reported lifecycle history

  1. Proposed

    Announced November 6, 2025; DPR Construction engaged as general contractor; three data centers, 929,000 sq ft total; first building target late 2027

    Underlying source
  2. Under construction

    Groundbreaking ceremony held November 6, 2025 per Vantage press release; active development underway with DPR Construction as general contractor.

    Underlying source

Source notes

Vantage's fourth Virginia campus; approximately 40 miles south of Washington DC in Stafford County (Fredericksburg region). Coordinates are county-centroid approximation — specific site address not confirmed in sources. Groundbreaking held November 6, 2025; DPR Construction engaged as GC.

Sources and provenance

Power Wars capture: 2026-11-02. Compute Atlas, CC BY 4.0. Entries are not independently verified by Power Wars unless stated.